10

-

Thursday, August 23, 1973

ADDITIONAL OFFICES FOR CHEUNG SHA WAN ABATTOIR

Five more offices will be added to the Cheung Sha Wan Abattoir

in Kowloon shortly to cope with the increase in the number of staff.

The rooms are to be built on the roof of the existing

refrigeration block.

Adjoining these new offices will be a room where lockers and

changing facilities will be provided.

A spokesman for the Urban Services Department said: "With

the increase of workload in the slaughtering services, more health

inspectors and workers have been posted at the abattoir, and expansion

of office accommodation is, therefore, necessary."

The expansion work, estimated to cost about $145,000, is

expected to begin in October and will take about five months to complete.

Release time: 7.30 p.m.