11 -

Friday, November 24, 1972

IMPROVED WATER SUPPLY TO TAI HANG

Residents of the Tai Hang and Jardine's Lookout areas will soon

have a much improved water supply with the laying of a new large diameter

fresh water main.

The total length of mains to be laid will be about 10,000 feet.

with a diameter of 15 inches. It will supply water from the Eastern Pumping

Station to the service reservoirs in the area.

The project is necessary because existing mains in the area cannot

cope with the rapidly increasing demand.

At the same time, an improved drainage system will be constructed

in part of Tai Hang.

The work involves the construction of 300 feet of reinforced

concrete stormwater box culvert in Lily Street and the laying of 290 feet

of sewer in Lin Fa Kung Street West.

The extension of the sewer will form part of the system for the

Lai Tak Housing Estate which is now under construction on the hillside

above.

/12

Share This Page