Wednesday, August 16, 1972

SUPPLEMENTARY PROVISIONS AMOUNT TO $125.5 MILLION

The Financial Secretary, the Hon. C.P. Haddon-Cave, told

the Legislative Council this afternoon that supplementary provisions for tho last quarter of the 1971-72 financial year totalled $125.5 million.

Of this sum, he said, Public Works Non-Recurrent expenditure accounted for $69.9 million, made up largely of $19.3 million required as a result of faster progress on existing projects and $40.3 million

due generally to increased.costs.

He explained that an additional $16.7 million was needed for major tunnel works for the High Island Water Scheme and a further $15.5 million for the raising of Plover Cove Dams, the uprating and extension of the Sha Tin Treatment Works and Pumping Station and the Tai Po Tau Pumping

Station.

The Government Printer needed another $2.7 million as a result

of increased consumption, higher cost of paper and other printing requisites

and for work let out to contractors.

The Financial Secretary explained that the latter was unforeseen

and consisted mainly of educational television books for school children and

fixed traffic penalty forms.

Supplementary provision of $22.5.million was required for the

purchase of a block of flats and for faster progress on capital works for

the Services under the Services Building programme,

"In accordance with the terms of the Defence Costs. Agreement, the

Hong Kong Government is committed to meeting expenditure on this programme

up to

£17 million during 1971-72, and to paying a cash contribution to bring

expenditure up to this amount in the event of under-spending."