SITE FORMATION FOR DESALTING PLANT
All Works Expected To Be Completed Next Year
Site formation works for Hong Kong's desalting plant, the largest
of its kind in the world, will begin next month.
The $450 million desalter, which will have a daily output of
40 million gallons, will be sited at Star Quarry near the 17 milestone on
Castle Peak Road.
The works include cutting back the existing cliff faces and
reclaiming an area of the seabed.
In addition, two miles of roadworks will be built. About a
quarter of a mile of pipeline will be laid to feed the desalted water
from the plant into Tai Lam Chung Reservoir. This will form part of the
supply system.
Intake works will be constructed to draw in fresh sea water to
the plant. The heavy brine will be discharged through an outfall stretching
about a mile on the seabed.
Marine works will involve putting up a fuel jetty to enable oil
tankers of up to 3,000 tons to berth alongside. A dock will be erected
for unloading the heavy plant.
"It is expected that all these works will be complated by the
end of 1973 so that the first of the desalter's six units can start production
by mid-1974," a spokesman for the Public Works Department said.
He added that all the units should be fully operative by the
end of 1975.