Return of all Public Works, Civil Roads, Canals, Bridges, Buildings, &c.,—Continued.

Describe the Work, and where situated.

ing or

Whether Estimated Construct Expenses

in

under

Authority under which it is executed.

When Com- menced.

Whether Finished

Amount of

Repairs.

■ Dollars.

or Un- finished.

Expenditure.

PUBLIC WORKS, EXTRAORDINARY,—Contd.

MISCELLANEOUS,— Contd.

Colonial Estimates

1922.

Fencing and protecting Football ground,......

Chinese Cemeteries,-Laying out new areas,

Construc. tion.

Cu-

4,800.00

82

Not commenced.

finished.

Do.

83

3,000,00 C.§.0. 20 in 63 of '22 | January, Continuing! 2.000.00

1922. ❘ work.

4,740.04

5,000.00

84

4,300.00 C.S.0, 3076 of '22

Miscellaneous Works,

Do.

6,000.00 C.8.0. 14 in 9% of '22

Do.

Do.

21,394.32

2,300.00 C.8.0. 3220 of '22 9.539.83 0.8.0.20 in 63 of '22

|

PUBLIC HEALTH and Buildings

ORDINANCE, 1903.

Compensation and Resumptions,

Do.

30,000.00;

85

Jan.,

1922.

Continuiug work.

8,912,26

WATER WORKS.

Enlarging mains to improve the distribution

system in Kowloon,

Do.

25,000,00

86

1920.

Uu- finished.

19,616,56

Extending Filter Beds near Lai Chi Kok.—

Two new Beds and Gauge Basin,

Do.

20,000.00

87

May, 1921. Finished.

61,019,67

Miscellaneous Water Works,

Do.

8,000.00

Jan., 1922, Continuing

work.

7,811.98

NEW TERRITORIES,

BUILDINGS.

Gaol, Ngau Shi Wau,

Do.

50,000.00

89

Not commenced.

Un- finished.

• 464.28

New Police Station, Shatin,......................

Do.

35,000.00

90

Do.

Do.

Erection of a brick Bungalow at Tai Po for

Public Works Department in place of the existing one,

Do.

20,000.00

1

91

Do.

Do.

Reconstruction of certain sheds at Laichikok.

Do.

20,000.00

92

Jan., 1922.

Do.

18,623.04

I

Clerks' Quarters, Tai Po,

Do.

3,504.19.8.0 20 in 63 of 722) 20,000,00

93

October, Finished.

27,245.96

1921.

Anglo-Chinese School, Cheung Chan,

Do.

17,000.00

94

Quarters for Inspector of Vernacular Educa-

tion in the New Territories, Taipo,

|| Do.

15,000.00

95

Do.

Un- Not commenced. Hnished.

Do.

|

Diaphone Fog Signalling Installation,

Waglan,

Block House for Police Castle Peak,

Do. {

96

Do.

97

ƒ❘ 13,400.0) C.8.0.1102 of 19, December, Finished.

15,000.00

11,000.00

27,130.97

1921.

Gn-

Land Bailiffs' Quarters, Ping Shan,...

Do. {

12,500.00 0.8,0. 3221 of 722 10,000.00

9H

Land Bailiffs' Quarters, Taipo, Extension

of Verandal on East side,

Public Latrines and Urinals,

}

Dec., 1922. finished.

March, Finished.

1921.

November, Not

30.00

€4,354.19

Do.

1,700.00

99

1,595.76*

1922. finished.

Do.

15,000.00

100

Not commenced.

Do.

• Expenses for levelling site.