| Describe the Work, and where situated | Whether Constructing or under Repair | Estimated Expense ($) | Authority under which it is executed | When Commenced | Whether Finished or Unfinished | Amount of Expenditure ($) |
|---|---|---|---|---|---|---|
| Central Police Station—Extension | Construction | 281,000.00 | Colonial Estimates 1918 | 11th Aug., 1916 | Finished | 42,676.61 |
| Import and Exports Office | Construction | 345,000.00 | Colonial Estimates 1918 | 12th July, 1918 | Finished | 9,129.71 |
| Rented Quarters for European Subordinates, Leighton Hill (6 Houses) | Construction | 94,000.00 | Colonial Estimates 1918 | Not commenced | — | — |
| Latrines and Urinals | ||||||
| (a) Trough Closet at junction of Castle and Robinson Roads | Construction | 2,200.00 | 4(a) | Aug., 1917 | Finished | 1,386.13 |
| (b) Urinal in Caine Road near Aberdeen Street | Construction | 2,500.00 | 4(b) | Aug., 1917 | Finished | 1,308.45 |
| (c) Latrine (10 seats) at Whitfield | Construction | 3,100.00 | 4(c) / C.S.O. 8 in 26 of 1918 | 24th Mar., 1918 | Finished | 3,822.71 |
| (d) Latrine (underground, 40 seats) at Staunton and Aberdeen Streets | Construction | 9,500.00 | 4(d) | Aug., 1917 | Finished | 8,866.36 |
| (e) Urinal (underground) at top of Caller Path | Construction | 2,200.00 | 4(e) | Aug., 1917 | Finished | 1,093.18 |
| (f) Urinal at foot of Breezy Path | Construction | 900.00 | 4(7) | Aug., 1917 | Finished | 701.78 |
| Describe the Work, and where situated | Whether Constructing or under Repair | Estimated Expense ($) | Authority under which it is executed | When Commenced | Whether Finished or Unfinished | Amount of Expenditure ($) |
|---|---|---|---|---|---|---|
| (a) Deep Water Bay to Tytam Tuk—Improvements to road for motor traffic, section from Deep Water Bay to Repulse Bay | Construction | 37,500.00 | 5(a) | Feb., 1917 | Finished | 40,180.71 |
| (b) Tytam Tuk to Tytam Gap—New road from north end of Tytam Tuk Dam to Tytam Gap | Construction | 55,300.00 | 5(b) / C.S.O. 16 in 26 of 1917 | Sept., 1917 | Unfinished | 35,398.59 |
| (c) Path from May Road Station to Tregunter Mansions | Construction | 3,800.00 | 5(c) / C.S.O. 1933 of 1917 | Jan., 1917 | Finished | 6,727.61 |
| (d) Aberdeen Road—Improvements in neighbourhood of Aberdeen Docks, and tow road past Aberdeen Village | Construction | 65,000.00 | 5(d) | June, 1917 | Finished | 63,065.90 |
| (e) Repulse Bay to Tytam Tuk—1st Section, new road | Construction | 80,000.00 | 5(e) | Mar., 1918 | Unfinished | 29,745.08 |
| (f) Repulse Bay to Tytam Tuk—2nd Section, improving and widening existing road | Construction | 66,000.00 | 5(f) | Mar., 1918 | Unfinished | 24,197.57 |
| (g) Tytam Gap to Shaukiwan—Improving existing road | Construction | 49,500.00 | 5(g) | Nov., 1918 | Unfinished | 6,166.95 |
---
Page 60–61
58
(F4)
Return of all Public Works, Civil Roads, Canals, Bridges, Buildings, &c.,—Continued.
Construct
Whether Estimated Authority under|
When
Describe the Work, and where situated.
ing or under
Expense
which it is
Com-
iu
executed.
menced.
Whether Finished or Un- finished.
Ainonat of
Expenditure.
Repairs.
Dollars.
20
3
Colonial Estimates 1918.
PUBLIC WORKS, EXTRAORDINARY.
HONGKONG.
BUILDINGS,
Central Police Station,-Extension,
Lui-
Con-
struction. 281,000.00!
11th Aug., finishel,
42,676.61
1916.
Import, and Exports Office,
Do. 345,000.00
2
12th July,
Do.
9,129.71
1918.
Rented Quarters for European Subordinates,
Leighton Hill, (6 Houses),.........
Do.
94,000,00
3
Not conmenseil.
Do.
Latrines and Urinals;—
(a.) Trough Closet at junction of Castle
and Robinson Roads,
Do.
2,200,00
4 (n)
Aug., 1917. Finished,
1,386.13
(b.) Urinal in Caine Road near Aberdeen
Street,
Do.
2,500.00,
4 (6)
D..
Di.
1,308.45
3,100.00,
4 (c)
24th Mar.,
(e.) Latrine (10 seats) at Whitfeild,
Do.
800.00
C.S.O. 8 in
Do.
3,822.71
1918.
26 of 1918.
(d) Latrine (underground-40 seats) at
Stauntou and Aberdeen Streets,
Do.
9,500,00
4(d)
Do.
Do.
8,866.36
(e.) Urinal (underground) at top of Caller
Path,
Do.
2,200.00
+(P)
Do.
Do.
1,093.18
(A) Urinal at foot of Breezy Path.........................
Do.
900.00
4(7)
Do.
Do.
701.78
COMMUNICATIONS.
Roads :-
(a.) Deep Water Bay to Tytam Tnk.— Improvements to slapt for motor traffic section from Deep Water Bay to Repulse Bay,...
Do.
37,500.00)
5 (u)
Feb., 1917. Du.
40,180,71
(6) Tytam Tuk to Tytum Gap,-New
55,300,00
road from north end of Tytam Tuk Do. Dam to Tytam Gap,
5,400.00
5 (6) C.8.0. 16 in 26 of 1917.
¡Sept., 1917.
Un- nill.
35,398.59
(c.) Path from May Rond Station to Į
Tregunter Mansions,
3,800,00
Do.
4,458.00
5 (c) C.8.0. 1933 of 1917.
Jan., 1917. Finishal.
6,727,61
(d.) Aberdeen Rowl,—Improvements in neighbourhood of Aberdeen Docks, and tow road past Abordeon Village,
Do.
65,000,00
5 (d)
June, 1917.
Do.
63,065.90
(e) Repulse Bay to Tytan Tuk-1st
Section-new rond,
Do.
80,000,00
5(e)
Mar., 1918.
Un. finished.
29,745.08
(A) Repulse Bay to Tytam Tuk-2nd Section Improving and widening existing rond,
Do.
66,000,00
5 (/)
Do.
Do.
24,197.57
(9.) Tyram Gap to Shaukiwun,—Im-
proving existing rond,
Do.
49,500.00
5 (g)
Nov., 1918.
Do.
6,166.95
Page 60Page 61