8
Ismo of certificate.
Form 17.
Removal from re. gister.
Duties.
Form 18.
Form 13. Form 14.
BUILDING (ADMINISTRATION) REGULATIONS, 1956
Disciplinary
Board.
10. The Building Authority shall, subject to the payment of the prescribed fees, issue to every person, whose application for Inclusion in the register of contractors has been approved, a certificate of registration in the prescribed form, and a copy of the Ordinance and Regulations.
11. The Building Authority shall remove from the register the name of any registered contractor who dies or ceases to engage in building works,
12. (1) Every registered contractor shall sign an undertaking on the prescribed form which shall be submitted to the Building Authority prior to commencement of any building works. Such undertaking shall be deemed to be an assumption by the registered contractor of responsibility for the strict compliance with the regulations,
(a) Every registered contractor shall exhibit on the site of the building works, officially stamped, signed and dated, copies of all plans submitted by the authorized architect to and approved, stamped, signed and dated by the Building Authority.
(3) Every registered contractor shall notify the Building Authority in writing within 48 hours of any work of emergency for which he has been engaged.
(4) Every registered contractor who has been appointed to execute building works shall give continuous supervision during the execution of such building works to ensure that the building works are being executed in accordance with the regulations,
(5) Within fourteen days of the completion of any building works, the registered contractor executing such building works shall certify to the Building Authority through the authorized architect on the prescribed form that such building works liave been carried out in accordance with the regulations.
(6) Every registered contractor shall within fourteen days notify the Building Authority of any change in his business address.
13. (1) The Governor may appoint a Contractors' Board for the purposes of section 8 of the Ordinance.
BUILDING (ADMINISTRATION) REGULATIONS, 1956
(2) (a) The Contractors' Board shall consist of seven persons
of whom there shall be
(i) two registered contractors,
(ii) three authorized architects,
(ii) Building Authority or his representative, (iv) legal adviser.
(b) The Building Authority or his representative, one registered contractor and one authorized architect shall constitute a quorum,
(c) The Building Authority or his representative shall be chairman and the legal adviser, if present, shall have the conduct of the inquiry.
PART IV.
Plans and Nolices.
9
14. (1) All notices and plans required by the regulations Delivery of shall be delivered to the Building Authority either by post or by notices and leaving them at his office during office hours.
(2) In the case of any proposed building work in the New Territories, notices and plans may be delivered to the District Commissioner.
(3) After such delivery to the Building Authority, the period on expiry of which he shall be deemed to have given his consent to the building works under subsection (6) of section g of the Ordinance, shall be twenty-eight days.
(4) Where such plans are not in accordance with the provi- sions of these regulations the authorized architect shall pay the prescribed fee in respect of each further submission of such plans to the Building Authority:
Provided that no such fee shall be payable where in the opinion of the Building Authority the further submission was occasioned by a bona fide misinterpretation of such provisions or for other good cause.
plans.
15. (1) Every notice of intention to commence, carry out or Notices, resume any buikling works shall be clearly and correctly completed to supply the information required in the prescribed form.
(2) Such notices shall be signed by the owner or by his duly authorized agent and countersigned by the authorized architect who has been engaged.
Farm 4.