Validation
of under- taking lo Progre96 and extinguish. ment of rights. Schedule: Part L
Director of
Public
Works
given pro- visional
authority to
construct
2
2. (1) All public and private rights of navigation or fishing and all public and private rights of access, user, possession or occupation and all other public or private rights (if any) in, upon and over the Crown foreshore, seabed and land occupied by the undertaking in progress set out in Part I of the Schedule, and existing prior to the commencement thereof, shall be deemed to have been extinguished and to have ceased to exist on such com- mencement; and such undertaking is validated for all purposes notwithstanding that such work may have been undertaken or commenced without regard to such rights (if any) and without the authority of any enactment extinguishing such rights,
(2) Save as is provided by this Ordinance, no claim shall at any time be made our action brought or continued in respect of the extinguishment under this section in whole or in part of any public or private right or the injurious affection of any land or other property resulting therefrom.
3. The Director of Public Works is authorized provisionally and subject to the definitive approval of the Governor in Council to construct the undertaking set out in Part II of the Schedule.
PART II.
Undertaking now authorized.
[5. 3.)
A reclamation in Gin Drinkers Bay of approximately 103.8 acres of Crown foreshore and seabed bounded on the west by a rubble mound approximately 1,550 feet long joining the Crown foreshore of Tsing Chau Island to the mainland at a point adjacent to the southern boundary of Taun Wan Permanent Cemetery, Demarcation District 446 Lot No. 262. on the north by the high water mark of the foreshore of the mainland, on the south by the high water mark of the foreshore of Teing Chau Island and on the north-east and south-east by a line marked CBA on plan No. P. 1564A signed by the Director of Public Works and deposited in the Land Office and showing and delineating in rod the limits and extent of such reclamation.
Passed the Legislative Council of Hong Kong, this gth day of November, 1953.
(Secretariat 3/3181/54)
Deputy Clerk of Councils.
under-
taking.
Schedule:
Part II.
Provisions for com. pensation
to apply to under- taking in progress. (Ord. No. 40 of 1936).
The provisions for compensation set out in sections 7, 8 and g of the Public Reclamations Validation and Clauses Ordin- ance, 1936, shall apply to the undertaking in progress validated under section 2 of this Ordinance as if such undertaking in pro- gress were to receive definitive approval at the same time as the undertaking now authorized to be carried out subject to such approval.
SCHEDULE.
I'ART 1,
Undertaking in progress.
[s. 2.1
A rubble mound approximately 1,560 feet lang joining the Crown fore- shore of Taing Chau Island to the mainland at a point adjacent to the aouthern boundary of Tsun Wan Permanent Cemetery, Demarcation District 446 Lot No. 262, which rubble mound is delineated and coloured blue on plan No. F. 16544 signed by the Director of Public Works and deposited in the Land Office.