Validation

of under- taking in progresa and

extinguish

ment of rights. Schedule, Part I.

Public Works

2. (1) All public and private rights of navigation or fishing and all public and private rights of access, user, possession or occupation and all other public or private rights (if any) in, Upon and over the Crown foreshore, seabed and land occupied by the undertaking in progress set out in Part 1 of the Schedule, and existing prior to the commencement thereof, shall be deemed to have been extinguished and to have ceased to exist on such commencement; and such undertaking is validated for all purposes. notwithstanding that such work may have been undertaken or commenced without regard to such rights (if any) and without the authority of any enactment extinguishing such rights.

(4) Save as is provided by this Ordinance, no claim shall at any time be made or action brought of continued in respect of the extinguishment under this section in whole or in part of any public or private right or the injurious ection of any land or other property resulting therefrom.

T

Director of 3. The Director of Public Works is authorized provisionally and subject to the definitive approval of the Governor in Council given to construct the undertaking set out in Part II of the Schedule. provisional authority

to construct

under- taking. Schedule. Part II.

PART II.

Undertaking Now Authorized.

[5. 3]

A reclamation in Hung Hom Bay of approximately 31 acres of Crown. foreshore and seabed extending in a sea wall from the junction of Gillies Avenug and Winslow Street in a south-westerly direction for a distance of approximately 470 ft.; thence in a southerly"direction for a distance of approximately 2,130 fl; thence in a south-westerly direction for approximately 2200 ft. to a point on the existing sea wall 470 ft. north of KP.P. 25, Holt's Wharf, the limits and extent of such reclamation being shown and delineated in red on a plan numbered P. 1816 signed by the Director of Public Works and deposited in the Land Office.

Fassed the Legislative Council of Hong Kong, this 8th day of June, 1955-

Deputy Clerk of Councils.

(Secretariat a/5282/47)

Provisiona for com- pensation

to apply to

under- taking

in progresa

(Ord. No. 40 of 1936).

4. The provisions for compensation set out in sections 7, 3 and 9 of the Public Reclamations Validation and Clauses Ordinance, 1936, shall apply to the undertaking in progress validated under section 2 of this Ordinance as if such undertaking in progress were to receive definitive approval at the same time as the undertaking now authorized to be carried out subject to such approval.

SCHEDULE.

PART I

Undertaking in Progress.

(s. 21

A reclamation in Hung Hom Bay of approximately 48.0 acres of Crown foreshore and seabed. the limits and extent of which being shows and delineated in blue on a plan numbered P. 1616 signed by the Director of Public Works and deposited in the Land Office.