Q 30
165. Saigon Street at K.M.L. 49 Formation and Surfacing:-This work was satisfactorily completed.
166. Sai Kung Road Extension, East of N.K.I.L. 63-Anticipated development did not take place and no work was necessary.
167. Tsun Wan Market Road :-Streets abutting on new development were made up and re-surfaced.
168. Bridges Strengthening, New Territories :-The work, which was referred to in paragraph No. 190 (Tai Lam Chung Bridge) of last year's report was completed on 10th March.
169. Castle Peak Road, North of T.W.M.L. 8-Realignment, Regrading and Surfacing-Private work was insufficiently advanced to permit anything to be done.
170. Improvements to Area North-East of Bridge at Taipo Market:-This work was practically completed under Contract No. 28 of 1939.
WORKS NOT APPEARING IN ESTIMATES.
171. MacDonnel Road Bridge-Reconstruction:-This work was referred to in paragraph 115 of last year's report. Owing to alterations to the original proposal, an extension of contract time up to April 26th was granted on which date the contract was satisfactorily completed.
172. Praya East Reclamation Scheme:-Improvements were put in hand comprising the re-alignment of Queen's Road East and Hennessy Road at Arsenal Street Junction.
173. Kowloon Muk Fu Ferry Road :-Plans and contract were prepared and a tender accepted, but work had not commenced by the end of the year.
174. Extension of Tar Macadam Around Hangar, Kai Tak Aerodrome :-This work was carried out under the maintenance contract.
175. Access Road to New Kowloon Cemetery No. 8-Contract No. 26 was signed by Messrs. Kwok Voon Construction Co. on 3rd July, and the work was completed on 19th October.
LOAN WORKS,
176. Central Market:-Upon completion of the new central market, the surrounding footpaths were paved with tiles and all necessary adjustments were made to the levels in Jubilee Street.