P.W.E. New Kowloon,

Q 102

201. Filling in Areas North-West of Nan Chang Street and West of Tai Po Road. This work was referred to in paragraph 232 of last year's Report.

Good progress was made during the year, an area of 18.5 acres being reclaimed by the end of the year.

Estimates Expenditure $25,000.00 $18,526.40

202. Furniture. Please see paragraph 136 of this Report.

Estimates Supplementary Vote Expenditure $1,000.00 $2,000.00 $1,718.53 $3,000.00

203. Chinese Cemeteries. Laying out new areas. Work carried out under this head has already been alluded to in paragraph 34 of this Report.

Estimates Expenditure $6,000.00 $5,890.07

Water Works:

204. Distributing Water Mains. The following mains were laid during the year:

(a) 666 lin. ft. of 8" C.I. main in Waterloo Road, South from Prince Edward Road,

(b) 180 lin. ft. of 6" C.I. main in Maple Street, North East from Lai Chi Kok Road.

(c) 170 lin. ft. of 6" C.I. main in Cedar Street, North East from Lai Chi Kok Road,

(d) 655 lin. ft. of 6" C.I. main in Yen Chow Street, North from Apliu Street.

(e) 436 lin. ft. of 10" C.I. main in Prince Edward Road, Westwards from Lai Chi Kok Road,

(f) 560 lin. ft. of the 18" trunk main in Tai Po Road near Wong Chuk Street was moved Eastwards in order to clear building sites.

(g) 350 lin. ft. of 6" C.I. main in Prince Edward Road, West of Lai Chi Kok Road, as an extension to the 10" main.

(h) 300 lin. ft. of 5" C.I. main in Tung Chau Street. South East from Prince Edward Road.

(i) 190 lin. ft. of 10" C.I. main in Tong Mi Road, South from Prince Edward Road.

Estimates Expenditure $15,000.00 $11,757.02