P.W.E. New Kowloon.

98

Path to give access to certain dairy farm lots at Diamond Hill, Po Kong District. Repainting Government Telephone Box at Kowloon Tong. Preliminary work in connection with Tai Po Road Widening near No. 3 Mile Stone, and Electrical improvements and additions were carried out in two buildings. One ceiling fan and a telephone were installed.

Estimates $10,000.00

Expenditure $3,056.53

186. Water Works.-The only work of any importance carried out under this heading was:-

300 lineal feet of 6" C.I. main laid in an unnamed street in Wong Uk Village north from Castle Peak Road.

Estimates $4,000.00

Expenditure $1,170.20

187. Port Works.-Minor works of a miscellaneous nature such as fixing of sign boards and investigations in respect of the foundations of proposed works at Kai Tak, &c. were carried out during the year.

Estimates, $1,000.00

Expenditure, $208.68

188. Kowloon Tong Development Area at Kowloon Tsai- Extension of Roads (no surfacing).—This work was referred to in paragraph 172 of the Report for 1928 and in paragraph 216 of last year's Report.

The work was satisfactorily completed by the end of the year.

Estimates $5,000.00

Supplementary Vote $6,900.00

Expenditure $11,876.49

Total Estimates $11,900.00