Q 75

P.W.E. Hong Kong.

Sewers. The following length of sewers were completed at the end of the year.

21" diameter sewers 3,790.4 lineal feet.

27" 600.5

In addition a contract was let on the 29th May for the laying of subsidiary sewers but work was not commenced until the beginning of September owing to pressure of work caused by the Water Emergency and need for ordering special material from home. The following sewers had been constructed by the end of the year:-

Size. Description. Length. Locality. Position. Remarks. 6′′ Sewer. 460' Gloucester Road. From Percival Street to Canal Road East. Completed. 6" 460' "" From Canal Road West to Marsh Road. 6" 509' "" From Marsh Road to Tonnochy Road. 6" 287' "" From Tonnochy Road to Stewart Road. 6" 658' "" From Stewart Road to Fleming Road. 6" 480' "" From O'Brien Road to Luard Road. 6" 430' "" From Luard Road to Fenwick Street. 6" 460' Hennessy Road. From Percival Street to Canal Road East. 6" "" From Canal Road West to Marsh Road. 6" 555' "" From Marsh Road to Tonnochy Road. 6" 431' "" From Tonnochy Road to Stewart Road.
Share This Page