P.W.R. Kowloon.

46

P. W. R. KOWLOON.

70. Maintenance of Buildings.-Government Buildings were repaired and maintained in accordance with the usual recurring programme of works.

Estimates, $35,000.00 Expenditure, $31,844.84

71. Improvements to Buildings.-Under this head the following are the more important of the works executed :—

Tsim Sha Tsui Police Station-Concrete surface to the surrounding compound. Children's Playground-Increasing the height of the surrounding fence. Royal Observatory-Alterations to bathrooms. Kowloon British School-Roughening the surface of the playground to prevent slipping.

Estimates, $10,000.00 Expenditure, $4,935.97

72. Maintenance of Roads & Bridges. Improvements to Roads & Bridges.

Estimates, $80,000.00 Expenditure, $82,500.00

Approximately 37 miles of Roads.-The road surfaces were generally maintained in a satisfactory manner.

The following are particulars of the additional areas laid with improved surfacing during the year:-

1. Tarring and sanding, Square yards. 95,193 2. 2½" granolithic paving slabs laid on footways, 19,453 3. Substitution of 7" reinforced concrete surfacing for ordinary macadam, tarpainted, 14,740 Estimates, $2,500.00 Expenditure, $70,963.99 $2,228.09 $73,192.08

73. Maintenance of Telephones.-The lines and instruments were maintained in good order. The lines and instruments in the Kowloon-Canton Railway were also maintained in a satisfactory manner. Six additional instruments were installed.

Estimates, $2,500.00 Expenditure, $2,451.99
Share This Page