B. O. O. Work.
Q 20
Sai Yu Shek Cemetery-Areas which had been washed out were repaired, paths surfaced and channels formed.
Cheung Sha Wan Cemetery-Exhumed areas were levelled, and terraces re-formed. Paths, steps, and channels were formed. Undergrowth was cleared. A R.C.C. Bridge was constructed.
39. Reclamations.-The following is a statement of the private reclamations which were completed or in progress during the year:-
Area in sq. ft. M.L.'s 430 and 43, North Point, (nearing completion) 833,975 S.I.L. 510, Shaukiwan, (completed) 8,530 S.I.L. 511, Shaukiwan, (completed) 6,960 S.I.L. 512, Shaukiwan, (completed) 5,130 S.I.L. 524, Shaukiwan, (completed) 7,626 S.I.L. 526, Shaukiwan, (in progress) 12,650 K.M.L. 93, Tai Wan, (in progress) 72,350 K.I.L.'s 1558 to 1561, Ma Tau Kok, (progressing early in the year, but work was suspended during the year) 407,985 N.K.M.L. 3, Lai Chi Kok, (in progress) 140,250 N.K.M.L. 6, Lai Chi Kok, (in progress) 374,400 N.K.M.L. 7, Lai Chi Kok, (in progress) 630,000 N.K.I.L. 520, Castle Peak Road, (work was suspended early in the year) 27,000 N.K.I.L. 521, Castle Peak Road, (work was suspended early in the year) 24,750 N.K.I.L. 971, Castle Peak Road, (work was suspended early in the year) 24,750 Tsun Wan M.L. 2, (completed) 874,400 Tsun Wan M.L. 4, (in progress) 74,901 Tsun Wan M.L. 5, (in progress) 273,600