Works & charges defrayed from funds not provided for under P.W.E. Votes.
88
NEW KOWLOON.
217. Training Stream Course in the New Cemetery Area, Ho Mun Tin.—This work which was referred to in paragraph 140 (c) of last year's Report, was completed by the end of September.
Sup: Vote, Expenditure,
$25,000.00 $22,311.67
NEW TERRITORIES.
218. Widening Castle Peak Road to 60 feet wide and filling in areas at Cheung Sha Wan.—A contract for this work was let to Messrs. Lee Fat & Co. on 23rd July for a sum of $13,296.80.
The work consisted of
(a) Forming a 60 ft. road from the junction of Tai Po Road and Nam Chang Street to Castle Peak Road along the Town Planning Alignment.
(b) Widening the existing Castle Peak Road to 60 ft. to Wong Uk.
(c) Filling in certain low-lying areas at Cheung Sha Wan. By the end of the year good progress had been made.
Sup. Vote, Expenditure,
$20,000.00 $2,226.00
WORKS AND CHARGES DEFRAYED FROM FUNDS NOT PROVIDED FOR UNDER P.W.E. VOTES.
219. Upkeep of Government Garage Plant.—The plant was maintained in a good state of repair.
Estimates, Expenditure,
$1,000.00 $813.37
220. Upkeep and running expenses of motor lorries and cars.—All motor lorries and cars were subject to recurrent inspection and maintained in good running condition.
Estimates, Expenditure,
$27,000.00 $26,442.88
221. Upkeep of Motor and Steam rollers.—All motor and steam rollers were subject to recurrent inspection and maintained in good running condition.
Estimates, Supplementary Vote, Expenditure,
$8,000.00 $5,000.00 $6,378.45
Total, $13,000.00