Q165
Harbour Developments.
Sewers. The following lengths of sewers and storm water drains are now completed, viz:-
Sewers. 21" diam. 2,290 L.F.) 2,290 or % of 24" 4,285 4,285 × 100 = 53.4%
S.W. Drains. 15" diam. 1,045 L.F. 18" 945 21" 105 27" 200 30" 220 39" 315 48" 175 54" 340 11'6" 440 3,785 or % of 12,130 × 100 = 31.2%
The following table is an analysis of the expenditure during the year under review :-
Head of Expenditure. Expenditure During the year ended 31.12.26. Previously. Total to 31.12.26; "CURRENT ACCOUNT". Contract No. 12 of 1921... Bonus payments Contract No. 12 of 1921 Items Subsidiary to; but not included in Contract No. 12....... $394,227.40 $1,039,964.49 $1,434,191.89 266,908.36 212,067.56 478,975.92 219.88 4,676.42 4,896.30 Dredging 1,989.28 93,883.42 95,822.70 Alteration to Existing Sewers 48,266.35 69,289.81 117,556.16 Alteration to Existing Storm Water Drains 20,591.37 154,836.62 175,427.99 Water Mains 89.69 Roads 181.48 31.51 30.50 121.20 211.98 Reconstruction of Buildings, &c., in R. N. Arsenal Yard Advance Account Salaries and Supervision.... 31,162.51 105,541.84 115,944.84 105,541.84 147,107.35 Total...... $763,646.30 $1,796,217.01 $2,559,863.31The account in respect of the contribution by Government towards the Fund for the Reclamation is as follows:-
1926 Estimates, ... $160,000.00 1926 Expenditure, $128,092.00 Expenditure to 31.12.26, $544,391.00