Q. 92

(b.) Main Sewer from Fuk Tsun Heung to Kaulungtong, East of the Railway. This work, referred to in paragraph 179 (b) of last year's Report was completed as under:-

Size Description Length Locality Position Remarks 30" & 27" Sewer 2,310' Mong Kok 33" & 30" " 1,620' Fuk Tsun Heung 24"21" & 18" Section 1 from K. I. L. 1724, Oak Street, to Mong Kok Nullah. Completed 22" Section 2 from Fuk Tsun Heung to K.I.L. 1724, Oak Street. 3,040' Kaulungtong 18" Section 3 from Mong Kok Nullah to 100' main cross roads near Kowloon Hospital. 422' Section 4 from main cross roads near Kowloon Hospital to Boundary Street. 9" & 6" From main 100' cross roads North West of Kowloon Hospital to Kowloon Hospital. 1,136'

1926 Estimates, $60,000.00

1926 Expenditure, $39,726.53

Expenditure to 31.12.26, $101,715.27