Q 105

P.W,E. Kowloon.

(b.) Matauchung, training and diverting main stream-course. This work was referred to in paragraphs 174 (c) of the Report for 1923 and 182 (c) of that for last year.

Good progress was made during the year. Excavation and piling for the foundations were completed and 400 lineal feet of walling was built and the concrete invert laid.

The circular culvert portion was also constructed for a length of 300 feet.

1925 Estimates, $40,000.00 Total Estimates, $50,000.00 1925 Sup. Vote, 10,000.00

$80,457.89 Expenditure to 31.12.25, $29,488.76

(c.) Homuntin District, Training stream-course in Cemeteries Area.—This work, referred to in paragraph 182 (d) of last year's Report, was not proceeded with during the year; there was consequently no expenditure under this heading.

1925 Estimates, $1,000.00 1925 Expenditure, Nil.

(d) General Works.-The extension of the nullah Northwest of K.I.L. 1150 in culvert form to Kowloon City Road referred to in paragraph 182 (e) of last year's Report was completed. To combat mosquito breeding, a considerable amount of trenching was carried out in Kowloon, South of Boundary Street, between the Railway and Kowloon City.

1925 Estimates, $10,000.00 1925 Expenditure, $1,973.15

179. Miscellaneous Drainage Works:-

(a.) Matauchung District, stormwater drainage. This work, referred to in paragraph 183 (a) of last year's Report, was proceeded with during the year and satisfactory progress made.

...

1925 Estimates, $30,000.00 1925 Expenditure, $20,624.22

Total Estimates, $30,000.00 Expenditure to 31.12.25, $20,624.22

(b.) Main sewer from Fuk Tsun Heung to Kaulungtong, East of the Railway. This work was continued and good progress made.

1925 Estimates, $30,000.00 Total Estimates, $70,000.00 1925 Sup. Vote, 40,000.00

1925 Expenditure, $70,000.00 $61,988.74 Expenditure to 31.12.25, $61,988.74