P.W.E. Kowloon.
(d.) Tokwawan Road (100 feet wide) Section between Kowloon City Road and K.M.L. 90 (estimates for 50-foot width). This work was referred to in paragraphs 173 (d) of the Report for 1923 and 179 (d) of that for 1924.
Fair progress was made throughout the year.
80,000 e. yds. of spoil from the line of Road was deposited in the Kowloon Bay West Reclamation and 397,000 sq. ft. of land, which was levelled to proper formation levels for exchange purposes, provided additional filling amounting to 135,000 c. yds.
1925 Estimates, ...$100,000.00 Total Estimates, 1925 Expenditure, $88,891.36 Expenditure to 31.12.25, ...$297,000.00 $260,231.33
(e.) Argyle Street,—Extension to its junction with Waterloo Road-This work was referred to in paragraphs 173 (e) of the Report for 1923 and 179 (e) of that for last year.
In spite of the large amount of rock met with, fair progress was made during the year.
1925 Estimates, ...$50,000.00 1925 Expenditure, $5,600.00 Total Estimates, ...$60,000.00 Expenditure to 31.12.25, $20,241.94
(f.) New Road through King's Park & Cemeteries area, Homuntin. Formation of 30 foot width and Bridge over Railway 60 feet wide.—This work was referred to in paragraph 179 (f) of last year's Report and that portion within the King's Park Recreation Area was completed by the end of the year.
1925 Estimates, ...$80,000.00 Total Estimates, $160,000.00 1925 Expenditure; $35,821.18 Expenditure to 31.12.25, $55,644.25
(g.) Macadamizing & Tar-painting main Roads.-This work was not proceeded with owing to the prevailing labour conditions.
1925 Estimates, 1925 Expenditure, $210,000.00 Nil.
(k.) Widening Salisbury Road to correct alignment.—This work was not proceeded with owing to the prevailing labour conditions.
1925 Estimates, 1925 Expenditure, $10,000.00 Nil.