ANNEXE B-Continued.

HEADS AND SUB-HEADS.

ESTIMATED. ACTUAL. INCREASE. DECREASE.

Brought forward,........

Hongkong,—Continued.

Drainage.

32. Training Nullahs :—

(a) Conduit and Hatton Roads Development Scheme,

(b) General Works,

33. Miscellaneous Drainage Works :-

(a) Extending existing outfall from below Wanchai Gap to the sea at a point near Aberdeen,

(b) Laying sewer in connection with Conduit and Hatton Roads Development Scheme,..

(c) Shaukiwan Road, Laying drain in connection with North Point Fore-shore Development,

(d) General Works,

$ c. 2,318,000.00 2,098,776.63 C. 710,516.54 929,799.91 931,905.26 1,172,265.04 8,000 21,136.41 20,000 3,107.79 19,463.95 4,892.21 4,892.21 536.05 5,500.00 6,036.05 20,000 14,193.57 5,806.43 5,806.43 8,000 1.76 7,998.24 7,998.24 20,000 35,000 6,314.69 82,831.74 13,685.31 47,831.74 47,454.27 377.47

Miscellaneous.

34. Queen's Statue Pier,

35. Quarry, Workshop and Plant,

36. Portable Tar and Asphalt Mixer,

37. Two 2-ton Motor Lorries,

38. New Ferry Piers,

39. Ferry Piers for Vehicular Traffic,

40. Forming rubble mound for protection to proposed reclamation, North Point,

41. Furniture for Government Offices and Quarters,

42. Aplichau,-Reclamation Scheme,

43. Harbour Developments,

44. Chinese Cemeteries,-Laying out new areas,

45. Chair Coolie Shelters,

46. Sanitary Depôt, Watson Street,

47. Motor Roller, 8 to 9 tons, for Asphal-tum work,

48. Kennedy Town Reclamation,exclusive of wharfage,

49. Miscellaneous Works,..

37,000 32,630.90 4,369.10 38,000.00 42,369.10 50,000 45,869.08 4,130.92 4,130.92 15,000 15,000.00 15,000.00 16,000 14,614.20 1,385.80 1,385.80 5,000 524.69 4,475.31 4,475.31 10,000 529.77 9,470.23 9,470.23 30,000 152.58 29,847.42 29,847.42 30,000 50,024.60 20,000.00 21.60 10,000 69.80 9,930.20 9,930.20 5,000 35,008.05 33,500.00 3,491.95 3,500 3,338.30 161.70 161.70 3,200 2,693.00 507.00 507.00 7,000 7,000.00 13,000.00 20,000.00 7,000 6,384.64 615.36 615.36 1,000 1,000.00 1,000.00 30,000 63,478.06 33,478.06 32,672.04 806.02

Public Health and Buildings Ordinance, 1903.

50. Compensation and Resumptions,

Water Works.

51. Eastern District Filter Beds, &c.,

52. Taitam Tuk Scheme,--Additional Pumping Plant :-

(a) Engine House and Foundations,

(b) Engine and Boiler,

53. Stanley Mound East, Catchwater..................

54. Mount Parker East, Catchwater,

55. Violet Hill (only half area), Catch-water,

50,000 1,836,134.05 1,786,134.05 1,500,409.28 285,724.77 100,000 96,702.35 3,297.65 50,000 16,472.77 33,527.23 200,000 275.23 199,724.77 80,000 76,111.51 3,888.49 50,000 96.12 49,903.88 10,000 15,034.39 5,034.39 40,000.00 34,965.61

$3,236,800.00 4,520,834.22 | 2,633,027.43 1,340,893.21 2,662,440.85 1,678,375.90 308,069.27