P.W.E. Kowloon,
-122
(d). Homantin District,—Training stream-course in new Cemetery Areas.—This work, referred to in paragraph 174 (d) of last year's Report, was not proceeded with during the year; there was consequently no expenditure under this heading.
1924 Estimates,
1924 Sup. Vote,.........
$1,000.00 9,000.00
$10,000.00
Nil
1924 Expenditure,.....
(e). General Works-The nullah North-west of K.I.L. 1150 was extended in culvert form to Kowloon City Road.
To combat mosquito breeding, a considerable amount of trenching was carried out in Kowloon, South of Boundary Street between the Railway and Kowloon City.
1924 Estimates,
$10,000.00
1924 Expenditure,...............$9,395.81
183. Miscellaneous Drainage Works :-
(a). Matauchung District, stormwater drainage. This work, referred to in paragraph 175 (a) of last year's Report, was not proceeded with during the year; there was consequently no expenditure under this heading.
(b). Main sewer from Fuk Tsun-heung to Kau Lung Tong, East of the Railway-This work was commenced.
(c). Kau Lung Tong Old Village Area, Main storm-water drain to Mong Kok Tsui Nullah.—This work was not proceeded with during the year; there was consequently no expenditure incurred.
(d). Waterloo Road Extension, storm-water drainage.—This work was not proceeded with during the year; no expenditure was in consequence incurred.
(e). General Works.-Owing to unsatisfactory tenders, most of the 6" and 9" Sewers, etc., were laid departmentally, the larger works being let by contract. The following are the most