180. Miscellaneous Drainage Works :-
(a). Extending existing outfall from below Wanchai Gap to the sea at a point near Aberdeen.—This work, referred to in paragraph 122 (a) of last year's Report, was completed at the end of the year.
1924 Estimates, $20,000.00
1924 Expenditure, $14,193.57
(b). Laying sewer in connection with Conduit and Hatton Roads Development Scheme. This work, referred to in paragraph 122 (b) of last year's Report, was not proceeded with during the year; there was consequently no expenditure under this heading.
(c). Shaukiwan Road.-- Laying drain in connection with North Point Foreshore Development. This work referred to in paragraph 122 (d) of last year's Report was continued.
1924 Estimates, $20,000.00
1924 Expenditure, $6,314.69
(d). General Works.-Owing to receipt of unsatisfactory tenders, most of the 6" & 9″ sewers, &c. were laid departmentally, the larger works being let by contract. The following are the most important stormwater drains and sewers which were laid during the year :-
Size Description Length in feet Locality Position Remarks 6" Sewer 1,365'0" Pokfulam Barker Road 6" 1,520'0" Victoria Road 6" 1,860'0" Victoria Road R.B.L. 160 & adjacent lots Completed 6" 2,160'0" New Motor Road From Peak Tramway Terminus to a point opposite R.B.L. 97 L.Ls. 2348, 2355 & 2357 to the sea 6" 635'0" Stubbs Road From Wanchai Gap along Stubbs Road 395'0" in the direction of Magazine Gap 6" From Stubbs Road to "Cadzow" R.B.L. 66 6" 1,297'0" Bowen Road From Stubbs Road to From Bowen Road to R.B.L. 193 6" 691'0" Sai Wan Ho In scavenging lane at rear of S.I.Ls. 481 & 482