P.W.E. Kowloon.

Q 116

(g.) A temporary 3" W.I. main, 550 feet long, was laid along Public Square Street, from Reclamation Street to the Praya Wall (Yaumati).

1923 Estimates, $15,000.00 Total Estimates, ......$50,000.00

1923 Sup.Vote, ................ 948.41 $15,948.41

1923 Expenditure,...$15,839.11 Total Expenditure,...$58,968.04

185. Miscellaneous Water Works.—The following is a statement of the expenditure on works carried out under this heading:-

(1.) 10" C.I. Draw-off from Kowloon Storage Reservoir was replaced by a 12" C.T. Pipe,

(2.) Electric Lighting Service for Water Works Bungalow at Kowloon Reservoir,

(3.) Unforeseen works, which included :—

(a.) Clearing stream-course near Kowloon Bungalow,

(b) Putting in 6" pipe at No. 3 stream, Shek Lai Pui,

(c.) Diverting 5" main near Bedford Road,

$971.44

$50.00

3,549.65

(d.) Evaporimeter at Kowloon Reservoir,

(e.) Improvements at Kowloon Filter Beds,

(4.) Minor extensions to mains,

$115.39

5,486.48

1923 Estimates, $8,000.00 $5,486.48

1923 Expenditure,

P.W.E. NEW TERRITORIES.

186. Gaol, Ngau Shi Wan.-This work was referred to in paragraph 173 of last year's Report. Sketch plans and small scale layout schemes were prepared during the year for a prison on the Kai Tack Reclamation.

The schemes were under consideration at the close of the year.

$50,000.00 Total Estimates,

1923 Estimates,

1923 Expenditure,...$44.43

Expenditure to 31.12.23,.. $15,053.18