P.W.E. New Territories,

Q 104

Work was started in August, 1922, and by the end of December all of the 4" piping, a total length of 15,000 lin. feet, had been laid. The strainer tank was completed and the stream intake well in hand.

1922 Original Vote,..... 1922 Sup. Vote,

$12,000.00 7,861.27

Total...... $19,861.27

1922 Expenditure, $19,856.57

197. Fanling Water Works Scheme. The original scheme for the supply of water at Fanling to the Golf Club was started in December, 1920, and completed in March, 1921.

The 4" main of the original scheme ended in the Club House Access Road at a point in front of the Garage.

In May, 1922, it was decided to extend the existing works so as to give a supply to houses on Castle Peak Road and also at Kam Tsin Village.

Work was started in July, 1922, and was completed in September.

The existing 4" main was extended along the Golf Club Access Road for a distance of 500 feet, and a 3" main 5,000 lin. feet in length now extends along the main Castle Peak Road as far as Kam Tsin Village.

1922 Estimates,. 1922 Sup. Vote,

$5,000.00 10,300.00

Total...... $15,300.00

1922 Expenditure, $10,832.53

WORKS NOT APPEARING IN ESTIMATES.

HONGKONG.

198. Conversion of Certain Houses on ML. 381 for use as a Fire Station. This work was undertaken at the latter end of the year, the top floor of the existing building being converted into two five-room flats, Offices, Stores, &c., and the ground floor into Mess, Quarters, Engine-house and Appliance Rooms. It was approaching completion at the end of the year.

1922 Estimates, 1922 Expenditure,

$12,348.18

199. Alterations to “Harbour View" as a Police Training School. This work consisted of alterations and additions to accommodate 1 Married Inspector, 1 Married Sergeant, 3 Instructors, 20 recruits, 40 Indian recruits and their Instructors, and 60 ...