With your permission, I would like to lay on the table this report with details on estimated costs and completion dates.

HONG KONG URBAN COUNCIL

Page 31 of 154

31

APPENDIX A

SCHEDULE A

over.

ADJOURNMENT — 5.01 P.M.

CHAIRMAN (in English):-The business of today's meeting is now Council stands adjourned until Tuesday, 17th June, 1975 at

4.00 p.m.

UNDER CONSTRUCTION

Project Anticipated Completion Date Estimated Cost $ m. Tender Price $ m. Saving $ m. 1. Beach Building at Middle Bay Beach May 1975 0.380 0.220 0.160 2. Beach Building at Stanley Main Beach June 1975 0.300 0.232 0.068 3. Beach Building at South Bay Beach June 1975 0.480 0.271 0.209 4. Changing Rooms and Showers at Big Wave Bay Beach June 1975 0.307 0.218 0.089 5. Changing Rooms and Showers at Shek O Beach August 1975 0.352 0.229 0.123 6. Mong Kok Market February 1975 3.900 2.908 0.992 7. Reclamation Street Cooked Food Bazaar May 1975 0.110 0.075 0.035 8. Cooked Food Bazaar at Kwun Tong Ferry Concourse June 1975 0.150 0.133 0.017 9. Refuse Collection Point at Minden Row, Tsim Sha Tsui May 1975 0.190 0.145 0.045 10. Refuse Collection Point at Shung Yan Street, Kwun Tong June 1975 0.070 0.060 0.010 11. Refuse Collection Point at Yan Oi Village June 1975 0.070 0.062 0.008 12. Refuse Collection Point at Walnut Street, Tai Kok Tsui July 1975 0.055 0.044 0.011 6.364 4.597 1.767

TENDERS INVITED

Project Anticipated Completion Date 13. Tai Wan Park and Swimming Pool, Stage I Mid - 1977 (Piling started on 13th May 1975) 14. Refuse Collection Point at Mansion Street, North Point September 1975 15. Refuse Collection Point at Hong Ning Road, Kwun Tong October 1975 16. Refuse Collection Point at Lai Yip Street, Kwun Tong October 1975 17. Wong Chuk Hang Cooked Food Bazaar, Aberdeen October 1975 18. Lai Yip Street Cooked Food Bazaar, Kwun Tong October 1975 19. Wai Yip Street Cooked Food Bazaar, Kwun Tong October 1975

SCHEDULE B