Staff $52,120

APPENDIY

APRENDIA B

DETAILS OF EXPENDITURE

for a period of 9 months.

2 Asst. Engineers....

1 Inspector of Works.

2 Foremen 01. II....

2 Foremen C1. III.

Accommodation (subsistence) Allowances.

Cheung Chau Pier

.$18,000

10,000

6,300

3,780

14,040

$52,120........$ 52,120 -

Reclamation wall....

$113,355

Reinforced concrete to pier.....

169,985

Rails, bollards, lighting to pier...

4,560

Timber fendering to pier......

20,600

Establishment..

1,500

$310,000

..$310,000

Tai O Pier

Pierwork

Rubble to foundations,

Granite pitching.

.$ 99,280

20,820

Earth fill.............

8,350

Mass concrete to foundations..

205,100

Plain concrete to deck & steps.

24,300

Fendering....

9,650

Establishment.

2,500

$370,000

$370,000

Roadwork

Pitched slope to Causeway.

...$27,000

Earthworks.

Surfacing & drainage

8,000

15,000

$50,000

........

.$ 50,000

[Hongkong & 203d]

$

Total..

$782,120

(f 48,883)