-2-

treatment outside the ordinary.

(b) TSUN WAN: If we are to avoid being substantially

out of pocket on the move it is essential that we recover our

expenditure on Tsun Wan. On the assumption that the Government

desire to see us move to Yau Tong (and it is only on this

assumption that the move will take place) could we reckon on

the Government taking over our existing Contract at Tsun Wan?

For your information on the basis of the Contract already signed

the total all-in cost, including sea walls, reclamation, cost

of land, etc., comes out at approximately $429,100 or $0.201 per

sq. ft.

(c) To enable us to go further into the question of

the cost of reclamation at Yau Tong we should like your

permission for ourselves and/or possible Contractors to carry

out any tests required concerning the nature of the soil,

including a survey of the district. Further, a nullah will

be required to take the storm water from the hill land behind

the reclamation and we shall be pleased if you will give us

your recommendation as to the cross sectional area of the

nullah required.

In conclusion we should very much like to take this

opportunity of thanking you for the ready help you have given

us and for the trouble to which you have already gone in

connection with this matter.

We have the honour to be, Sir,

Your obedient servants,

For THE ASIATIC PETROLEUM COMPANY(S.C.)LTD.,

J. K. Bousfield.

Dict:JKB/DC.

The Hon. The Director of Public Works,

Hong Kong.

17