Works.
HEAD 1. New Markets:-
(a) Central Market
Head 1. Total
Appendix VI (C).
LOAN WORKS.
Additional Works to be charged to a proposed New Loan.
Estimated Cost.
*115,312.50
115,312.50
123
311
Actual Expenditure 1937.
Revised Estimated Expenditure 1938.
Estimated Expenditure 1939.
Estimated Expenditure 1940.
$
115,312.50
115,312.50
HEAD 2. Water Works--
Authorized Works.
(a) Supply to Albany
(b) Supply to Peak Road
(c) Cross Harbour Pipes
100,000.00
1,521.19
85,000.00
18,478.81
100,000.00
1,505.06
90,000.00
8,494.94
950,000.00
4,859.07
710,000.00
235,140.93
(d) Rapid Gravity Filters, Eastern
300,000.00
1,000.00
50,000.00
240,000.00
(e) Kowloon Chai Service Reservoir
240,000.00
3,058.93
50,000.00
170,000.00
16,946.07
(f) Supply Main to Kowloon Chai Service
Reservoir
250,000.00
200,000.00
50,000.00
(g) Distribution Island
100,000.00
1,368.61
30,000.00
35,000.00
33,631.39
(h) Distribution Mainland
75,000.00
4,221.91
25,000.00
25,000.00
20,778.09
(i) Shing Mun Valley Scheme Catchwaters
1,070,000.00
40,253.53
220,000.00
406,000.00
408,746.47
Proposed New Works:-
(j) Rapid Gravity Filters, Shing Mun Valley
Scheme
150,000.00
100,000.00
50,000.00
(k) Tai Lam Chung Scheme, Preliminary Works.
25,000.00
25,000.00
(1) New Meters
120,000.00
60,000.00
60,000.00
(m) Waste-Detection Equipinent
300,000.00
120,000.00
180,000.00
(n) Reconstruction at Albany
150,000.00
10,000.00
140,000.00
(0) Miscellaneous Works
67,500.00
67,500.00
Head 2. Total
Grand Total
3,997,500.00
4,112,812.50
56.783.30
56,783.30
1,211,000.00
1,211,000.00
1,525,614.68
1,204,102.02
1,640,927.18
1,204,102.02
*Part Cost: total cost is $900,000.00 of which $784,687.50 is chargeable to 1934 Loan, Appendix VI (b).