Enclosure No. 2.

55

COLONIAL TREASURER:

Your Excellency,

Under Item 6 Airport (b) Airport and Seaplane Slipway the sum of $860,000 has been approved for the total

cost of these works. See Appendix VI (b) p. 115 of

Estimates, 1936.

Up to 31st December, 1935, $583,931.92 only had

been expended owing to delay in arrival of materials

although when the 1936 Estimates were framed it had been

thought that the larger sum of $708,695.86 might have been

expended up to the end of last year. The actual balance

remaining on 1st January, 1936, was therefore $276,068.08

against an estimated balance of $151,304.14. A resolution

has already been taken for the expenditure during 1936 of

the latter sum and I am now asking that the difference

between $276,068.08 and $151,304.14, namely, $124,763.94 be

also made available in order to complete the works this

year.