that for the Land Office to Messrs. Foo Loong & Co. Work was commenced on October 16th and both garages were com- pleted by the end of the year.
Expenditure
$3,025.22
229. Lady Ho Tung Infant Welfare Centre, Fanling.-This work was described in paragraph 190 of last year's report. The work proceeded satisfactorily during the year and was com- pleted by November. The land and cost of the building were provided by Sir Robert Ho Tung.
230. Resurfacing Taipo Road from Tai Wai Level Crossing in the direction of Taipo.-Margins, and an additional layer of 4' macadam, tarpainted and chipped, were laid between the 8 milestone. Tai Wai Level Crossing, and the 123 milestone, and improvements were made to the road alignment. The area cover- ed was 49,000 square yards.
Expenditure
$62,790.74
231. Improvements to Fanling Water Supply. In order to improve pressure on the system generally the following works were carried out during the year-A new intake was construct- ed at 286.59 O.D), approximately 76 feet above the then existing intake. A 5′′ wrought iron pipe 575 feet in length was laid connecting the intake with the existing twin 3′′ mains, cut- ting out the old strainer tank. A concrete strainer tank con- trolled by a ball cock and a steel storage tank of 30,000 gallons capacity, both having a T.W.L. of 229 O.D., were built on the hill near the 8th green, old course, 520 feet of 5" cast iron main being laid as a feed from the existing system to the strainer tank. Twin discharge pipes consisting of 737 feet of 4′′ wrought iron piping were provided from the storage tank and con- nected up with the existing golf club and village system. In addition 140 feet of 3" wrought iron piping were laid as a bye- pass to the two tanks.
Expenditure
$8,795.22
232. Water Supply to Sheung Shui Police Station.-4,120 feet of 2′′ wrought iron piping were laid from the Fanling cross roads to Sheung Shui Police Station.
Expenditure
$3,674.98
A
233. Formation of Dumping Ground at Kun Tong.-Instruc- tions to proceed with this work were received on 4-11-33. series of guide pile stagings and frames were erected and a survey was completed.
1933 Expenditure
$4,304.63
234. Archaeological Operations, Hami Wan Beach, Lamma Island. Explorations of an archaeological nature were under- taken in the large deposit of sand at this beach under the direction of the Rev. Father Finn, S.J., this Departinent providing all the plant, tools, labour, etc., necessary for the execution of the work.
$935.00
Expenditure
Q 55
LOAN WORKS.
235. New Gaol at Stanley. This work was referred to in paragraph 196 of last year's report. A Contract for the site formation was let to Messrs. Tung Shan & Co. for $261,751.50 on the 5th July, 1933, and good progress was made with the excava- tion and filling of the site and the construction of concrete foundations for the boundary wall and for several of the prison buildings. Work on the road to Wong Ma Kok Village, to serve the Prison site (see paragraph No. 197 of Report for 1932), which had been suspended on 22.9.32, was recommenced on 1.8.33 on the section of the road between pickets 0/00 and 19/50.
The question of compensation for the suspended period was under consideration at the end of the year.
1933 Expenditure............
.$115,664.58
Expenditure to 31st Dec., 1933..... $162.244.36
SHING MUN VALLEY SCHEME-1ST SECTION.
236. Item Q, Hong Kong Gardens Service Reservoir.—This work was referred to in paragraph 198 of last year's Report. The Reservoir, including the reinstatement of the gardens, and construction of various architectural features, was com- pleted during the year. During construction slight settle- ment of the main walls occurred at the N.W. corner of the reservoir and this was effectively dealt with by under- pinning and grouting. The Reservoir proved very satisfactory under test and was brought into use on 4th May. The excavation for the Reservoir, which amounted to 25,560 cubic yards, was mainly utilized at the site, the sulplus amounting to 6,880 cubic yards being removed and deposited at North Point Reclamation. The Reservoir, which is 276'-0" long by 180'-0" wide, has a capacity at a top water level of 240.25 A.O.D. of 4.957 million gallons, the average depth of water when full being 16′-6′′. A gravity section division wall of an average height of 10-3" divides the reservoir into two compartments, the capacity of the Eastern one being 1.590 million gallons, and that of the Western one 1.450) million gallons, whilst the capacity between the top of the division wall and top water level of the Reservoir is 1.917 million gallons. The 24" supply main. which brings water from the Shing Mun Valley via the Cross Harbour Pipe, discharges into a gauge basin in the Inlet Control House from which the water is directed into either or both compartments of the Reservoir by means of two 24′′ Penstock valves. Automatic recorders to measure the amount of water entering the Reservoir and also the height of the water in the Reservoir have been installed in the Inlet Control House. Two independent 18" diameter draw-off pipes, one from each compartment of the Reservoir and controlled by separate 15" Sluice Valves, discharge into a common 18" main for distribution to the City. The main walls of the Reservoir, the foundations of which required reinforced concrete piles for the North wall and the North end of the East and West walls, were constructed of