Enclosure No. 3.
50
Suggestions for consideration by Crown Agents when
drawing up agreement with Consulting Engineers.
Consulting Engineers to advise upon design and to
supervise the Construction of the Works in connection with
the erection of a Dam at the Shing Mun Gorge.
2. Consulting Engineers to prepare all necessary Designs,
Detail Drawings, Specifications, Bills of Quantities,
Schedules and any other particulars to enable the said Dam
to be carried out at the earliest possible date.
3.
Consulting Engineers to be free to carry out the
Works by Contract, Sub Contract or Direct Labour subject to
permission from Hong Kong Government after particulars have
been submitted.
4.
The Consulting Engineers shall supply the Government
with two copies (prints) of the General Drawings for the
Works before work is commenced and on completion shall
furnish two copies of drawings of the Works as carried out
showing foundations, drainage etc. with finished levels.
5.
Any alterations or additions to the Works which may
alter the Estimated Cost or alter the general nature of the
Structure should first be submitted to the Colonial Government
before being carried out.
6. Fees and mode and time of payment to be stated.
Period of Consulting Engineers Contract with Government to be
set, say, five years. Notice to be given six months before
expiry and if any extension necessary to be by further mutual
agreement.
7.
One of the Consulting Engineers to visit the Works
once in every year during the Construction of the Works.
8. Dispute or difference arising over the Works between
Government or Consulting Engineers and Contractors or Sub
Contractors, Consulting Engineers to be Arbitrators without
extra fee.
9.