COMPARATIVE STATEMENT OF THE ESTIMATED AND ACTUAL
Heads and Sub-Heads
Brought forward
Hend 31-PUBLIC WORKS EXTRAORDINARY,
HONG KONG.
BUILDINGS.
Sub-heads-
1 Additional Transmitting Block and
EXPENDITURE OF THE COLONY OF HONG KONG FOR THE YEAR 1930.
Estimated.
Actual.
Increase.
Decreas
visionally
Voted.
$
$
$
$
14,450,905
15,947,559.47 2,670,895.72 1,174,241.25
Explanatory Remarks.
More work done than anticipated.
Not begun until late in the year.
do. do.
Not begun.
Work completed in 1929.
Not begun until late in the year.
Not begun.
650.00 The foundation work proved more tostly than anticipated.
Mast at Cape D'Aguilar W/T Station,
20,000
2 New No. 2 Police Station
200,000
23,458.90 99,200.95
3,458.90
4,940.00
3 Sai Ying Pun New Market
200,000
13,521.89
4 Victoria Gaol--New Printing Shop
85,000
42,148.44
100,799.05 186,478.11 42,851.56
5 Junction of Ladder Street and Holly- wood Rond-Underground latrine (60 seats)
17,000
17,000.00
6 Spring Garden Lane and Cross Street
Latrine and Urinal (54 seats)
2,000
1,529.52
7 Sai Wan Ho-Increase of Pig Lairage.
500
8 Latrine and Bathhouse on Pruva Fast. 9 Latrine and Urinal at Rock Hill St.
25,000
5,380.17
470.48 500.00 19,669.83
(30) seats)
10,000
10,000.00
10 Latrine at Aberdeen (16 seats)
7.000
11 Alterations to Belilios School-Con-
version of two rooms into one
3.800
7,590.47
3,754.18
590.47
45.87
GENERAL WORKS.
12 Roads
70,000
49,869.17
20,180.83
Drainage :-
13 Training Nullahs
25,000
15,962.70
14 Sewage and Storm Water Drains
60,000
42.236.68
9,037.80 17,763.32
15 Miscellaneous
30,000
82,416.66
2.410,66
5,000.00
16 Water Works
15,000
17 Port Works
5,000
12,088.62 9,857.00
2,966.38 1,643.00
COMMUNICATIONS.
18 Road from Causeway Bay to Quarry
Bay section 70 ft. wide, opposite M.Is. 430 and 431
15.000
20,705.26
5,705.26
6,200.00
19 Tai Hang Development Road Con-
struction including strengthening Conduit
60,000
41,793.96
20 Barker Road improvement from Stubbs
Road to Victoria Hospital
19,000
17.811.64
21 Path 10 wide to Cape D'Aguilar
W/T (1st Section)
2,000
22 Road connecting Garden Road and
Bowen Road with May Road
88,000
1,709.21
117,970.82
18.206.04
1,188.36
290.79
29.970.82
30,000.00
23 Yee Wo Street-Re-alignment of tram
track and roadway between Great
George Street and Causeway Bay
100,000
94.604.09
5.335.91
24 Widening May Road from Tram
Station to Conduit Road to a
minimum width of 20 feet
75,000
21,015.39
53,984.61
25 To construct steps near I.L. 2801 to
give access to 100 ft. contour road
west of Tin Hau Temple
Carried forward
$
Carried forward
3
5,500
1,139,800
14,450,905
5,485.81
673,566.48
15,947,559.47
14.19
42,142.11
2,670,895.72
508,375.63
1,174,241.25
|
Work kept down in accordance with general policy to economise.
do. do.
Installation of modern asphalt and screening plant at Tsat Tze Mui Quarry. Economy.
do.
More work done than anticipated,
Overestimated.
Contract rates higher than anticipated and substitution of tar macadam for [ordinary dry macadam.
Overestimated.
This work was not carried beyond Aigburth Hall.