55
Estimated Cost.
3
Additions to Power Plant
12860
4.
Additions to Transmitting Plant 93400
5.
Additions to Receiving Gear
9000
6. Provision of automatic
transmitter
5280
Additional Power & Telephone
Cables
9000
8.
Alterations to Radio Counter
1000
9.
Tools and Instruments
1600
$ 165240
The total cost and division of cost of the
above items over a period of two years is:
Estimated Total
of present proposal.
To be expended during 1928.
£165240
$68790
To be expended during 1929.
$96450
Of the $68790 estimated for 1928, the
expenditure would become due approximately as follows:-
April
$1000
May
$3000
June
$6100
July
14000
Aug
16840
Sept.
1600
Nov.
2250
Dec.
24000
$68790.
-8-