HONG KONG AIRPORT.

Statement of Estimated Cost.

Total Estimated Expenditure of Present Approved

Scheme

Additional

Expenditure for Mr.

Dawson's Scheme

Remarks

93 end.

(a)

Resumptions.

1. Airport approved scheme

1,186,250.00

2. Gaol site

3. Extension proposed by Mr. Dawson

115,470.00 60,000.00

Expenditure to 31.12.27 $1,001,250.00. Previous expenditure by H.K. Government.

(b)

Forming of reclamation including com- pletion of sea walls, nullahs, surfacing and drainage.

1. Airport approved scheme

738,000.00

2. Gaol site

3. Extension proposed by Mr. Dawson

15,008.75 124,000.00

Expenditure to 31.12.27 $212,599.09. Previous expenditure by H.K. Government.

(c)

Covering of Nullahs.

1. Airport approved scheme

275,000.00

Expenditure to 31.12.27 $43,957.13.

2. Extension proposed by Mr. Dawson

36,000.00

(a)

Slipways, filling in Camber area, exten- sion of Nullah in Camber area and contin gent works.

1. Airport approved scheme

275,000.00

(e)

Roads.

1. Airport approved scheme

55,000.00

2. Extension proposed by Mr. Dawson

10,000.00

(f)

Gaol Foundations.

1. Gaol site

Totals

Add additional expenditure

Total for Mr. Dawson's scheme

Cost of Resumption of Extension proposed $80,000 of which $20,000 is included in item (a) 1. Note. No provision is made in these figures for the erection of buildings.

$2,529,250.00 625,978.75 $3.155.228.75

265,500.00

$625,978.75

Previous expenditure by H.K. Government

{