HONG KONG AIRPORT.
Statement of Estimated Cost.
Total Estimated Expenditure of Present Approved
Scheme
Additional
Expenditure for Mr.
Dawson's Scheme
Remarks
93 end.
(a)
Resumptions.
1. Airport approved scheme
1,186,250.00
2. Gaol site
3. Extension proposed by Mr. Dawson
115,470.00 60,000.00
Expenditure to 31.12.27 $1,001,250.00. Previous expenditure by H.K. Government.
(b)
Forming of reclamation including com- pletion of sea walls, nullahs, surfacing and drainage.
1. Airport approved scheme
738,000.00
2. Gaol site
3. Extension proposed by Mr. Dawson
15,008.75 124,000.00
Expenditure to 31.12.27 $212,599.09. Previous expenditure by H.K. Government.
(c)
Covering of Nullahs.
1. Airport approved scheme
275,000.00
Expenditure to 31.12.27 $43,957.13.
2. Extension proposed by Mr. Dawson
36,000.00
(a)
Slipways, filling in Camber area, exten- sion of Nullah in Camber area and contin gent works.
1. Airport approved scheme
275,000.00
(e)
Roads.
1. Airport approved scheme
55,000.00
2. Extension proposed by Mr. Dawson
10,000.00
(f)
Gaol Foundations.
1. Gaol site
Totals
Add additional expenditure
Total for Mr. Dawson's scheme
Cost of Resumption of Extension proposed $80,000 of which $20,000 is included in item (a) 1. Note. No provision is made in these figures for the erection of buildings.
$2,529,250.00 625,978.75 $3.155.228.75
265,500.00
$625,978.75
Previous expenditure by H.K. Government
{