61

- 2 ·

material could be deposited elsewhere and at no greater

cost would be:-

1,470,000 cubic yards @ 65 per cubic yard

=

$955,500.00.

The estimated cost of filling in the

Central and East Central sections of the Reclamation,

if filling material is taken from earth cutting on land, would be:-

1,607,100 cubic yards at

=

24€ $385,704.00.

per cubic yard

Total estimated cost of these two works

carried out separately

**

$1,341,204.00.

If these works are carried out together,

the estimated cost is:-

1,470,000 cubic yards § 65€ per cubic yard

= $955,500.00

137,100 c.yds.

@ 240 per c.yd¤ 32,904.00

Total:- $988,404.00

The difference in the estimated cost of

carrying out the works separately and together is

$352,800 in favour of the latter scheme. I would add that the cost of dredging would be very considerably enhanced, if the opportunity were not seized to make use of the Netherlands Harbour works dredgers which happen to be available now.

4. Not only is there a saving in cost, but there is also a saving in time. The

The dredging scheme is estimated to be completed in 18 months, whereas the filling in of the reclamation from earth cuttings on land would take probably more than double that time.

5. At a Meeting of the Finance Committee

on the 29th April, 1927, the Unofficial Members, while

approving

Share This Page