ITEM,
WORK.
ESTIMATED UNEXPENDED BALANCE TO
31.12.25.
$
SUPPLEMENTARY
| VOTES ALREADY
TAKEN,
ESTIMATED SUPPLEMENTARY
VOTE REQUIRED,
ESTIMATED
UNEXPENDED
ITEM.
WORK.
!
BALANCE TO 31.12.25.
SUPPLEMENTARY ESTIMATED
VOTES ALREADY SUPPLEMENTARY
TAKEN.
VOTE REQUIRED.
25,000
(2) Improvements to existing main roads for
motor traffic
100,000
(e) Argyle Street, Extension to its junction
with Waterloo Road
20,000
(f) New Road through King's Park and Cemeteries Area, Homantin: formation of 30 foot width and Bridge across Railway 60 feet wide
10,000
(g) Macadamizing and tar painting to new
Main Roads
PUBLIC WORKS, EXTRAORDINARY,-Continued.
Brought forward
PUBLIC WORKS,
EXTRAORDINARY,-Continued.
Brought forward...
1,546,000
1
204,000
553,900
959,000
134,600
294,800
106
Cheung Chau School
1,000
75 Extension to existing Market at Mong Kok Tsui.
F. M. 24
107
Un Long School
1,000
10,000
108
Gardeners' Quarters, Sheung Shui
10,000
리딩
76
Store for Government Materials near Railway.... Quarters for Clerical Staff .......
25,000
109 Taipo School...
20,000
200,000
110 Magnetic Huts
9.000
78
Police Married Quarters, Hung Hlona
79: Public Latrines, Urinals and Bath houses
15,000
111
Open Market, Kowloon City
15,000
10,000
112 Sanitary Inspector's Quarters, Kowloon City
25,000
COMMUNICATIONS.
COMMUNICATIONS.
80
Roads :-
114 Roads :--
(a) Main Roads, Kowloon
(f) Extension of Roads in Kowloon Tong
Development Area...
10,000
() Fanling to Shataukok Road
40,000 FM. 67
(Road to Shun Wan..
10,000
(k) Taipo Market to Kam Shan
2,000
(1) Widening two bridges at Au Tau and
F.M. 63
Kum Tsin
10,000
(0) General Works
48,500
DRAINAGE.
110,000
81
General Works
83,600
DRAINAGE.
82
Training Nullahs:-
(a) Mongkoktsui Nullah East, extension
through Railway Bridge.
115 Training Nullahs-
(a) One side wall and invert of nullah on Eastern side of the Kowloon Tong Development Scheme
(b) Kowloon Tong Development Area, connection of stream North of this area of main nullahı
26,000 Y
25,000
21,500!
(b) Matauchung training and diverting
116 Miscellaneous Drainage Works:-
main stream course
20,000
(c) Homuntin District. Training streain
course in New Cemeteries Area
F.M. 63
1,000
(a) Main sewer from Fuk Tsun Heung in a North-easterly direction of Taipo Road (e) General Works
F.M. 63
10,000
25,700
83
Miscellaneous Drainage Works :—
MISCELLANEOUS.
(e) General Worka...
114,000
118
MISCELLANEOUS.
84
Kowloon Bay West Reclamation 1st Section
30,000)
02
Forming and Levelling areas in Tai Shek Ku
Valley, F. M. 8
4,000
93
Compensation and Resumptions
10,000
50,000
Refuse Dump, -Cheung Sha Wan
122 Telephone cable between Kowloon, Tripo and
Fanling. F.M. 19...
123 Miscellaneous Works. F.M. 22..
124 Compensation and Resumptions
F.M.
2,500
16,000 7,000
F.M.
100,000 | 100,000 12
& 67
10,000 41 &
WATER WORKS.
67
New Territories.
125
Extension of Kowloon Catchwater
120
Shek Lai Pui, Reservoir and Contingent Works
10,000 30,000
BUILDINGS.
127 | Shing Mun Valley Scheme :—
99
Quarters for Government Officers, North of
Kowloon Tong Area
1,000
100
Erection of a Brick Bungalow at Taipo for
(b) Access road (Tsun Wan to Pine Apple
Pass)
(c) Temporary Intake and Conduit
Public Works Department in place of the
(d) North Conduit...
existing one
1,000
102
District Sanitary Office, Shamshuipo
25,000
103
New Lunatic Asylum
(a) Buildings
(b) Site
20,000
Tunnels and South Conduit
g) Filtering plant and erection
128 Kowloon Bywash Reservoir 120 | Fanling Water Works Scheme
25,000 15,000 25,000
F.M.
03
100,000
100,000
9,000
6,000
Bik
Carried forward
1,546,000
204,600
553,900
Total Public Works, Extraordinary.......
$1,947,000
$327,000
$863,000