List of a few onthly reporte to the con.D.P.W.
January 1909. Work in a backward state June 1909
H
do.
(I stated that Chan A Tong had been in- formed that no further payment would be made)
September 1909 Serious delay, and that other steps would have October
to be resorted to. May 1910.
June 1910.
July 1910.
August 1910.
Only two masons working to dome. Poor progress to steel framing of dome, fittings to courts de- layed for want of timber. Poor progress with tiling work. Two yards only of asphalt were laid. No timber available for fittings to courts. The contractor has promised to supply timber by the 1st August, failing which other steps should be taken in order to complete the work.
No timber for fittings to courts, Timber for casing to dome also required, delaying the whole work. Poor progress with dressing of granite work. Lo as and theft of tiles.
Timber required only 13 logs to hand. September 1910. Nothing done to dome. Poor progress with granite
October 1910.
work. Joiners required for fixing of pahelling and preparation of fittings to courts. Poor progress with granite work.
November 1910. Nothing done to fittings of Granite Great Court
December 1910.
40. do.
Timber not yet bought. A great amount of work has still to be done to fittings of second and Third courts.
January 1911.
No thing done to fittings of Great Court. of tiles still in progress.
Theft