$23,000) thus leaving the amunt at, approximately 481,000.

The contract date for the completion of the work was 16th

July 1906 which with extended time added (say nine months)

owing to the extra work would bring the date to the 16th April

1907.

The following schedule will shew the approximate value of

work executed year by year:-

To the end of the year 1903

$16,000

1904

69,077

1905

56,667

1906

82,821

1907

89,759

1908

83,631

1909

56,815

1910

13,550.

FITTINGS ETC: FOR COMPLETING THE BUILDING

The contract for this work was signed by the present Ir.

Chan A Ting on the 22nd February 1908 the amount being $124,271

09 and the date for completion was the 31st December 1909. A

little extra work has been ordered for which the Contractor

would be entitled to. say two months extra time, thus bringing

the date for completion to the end of February 1910.

With regard to the contract amount of g124,271.09 I have

to point out that a sum of $34,422. represents the value of

materials obtained from England and supplied by the Government

to the Contractor, thus leaving the value of work to be done

by him at $89,849.

The following schedule will shew the approximate value of

work executed year by year.

To the end of the year 1908

1909 1910

$3,000. 21,900

26,000

I now beg to comment upon the unfinished contracts as

follows:-

As regards the contract rate for the work at the time the

contract for the superstructure was entered into, I would point

out there was a building boom in in the Colony and Contractors