461

Resumption of Inland Lot 84.

.8275,000

-

-

do. Inland Lot 1918....

53,000

do. Marine Lot 111 (portion) and of

Inland Lots 443 and 616...........

Constructing the roads shown on Plan No. 1

34,920

traversing the Morrison Hill area, includ- -ing necessary retaining walls, &c.............. Constructing culvert along line of proposed 60

foot road for diversion of Wongeichong

Nullah and altering other drains..

37,580

150,000

Filling in Bowrington Canal...

5,000

555,500

Value of lots rendered available for sale:-

Areas coloured red on Plan No. 1

545,776 square feet at $1...

s.f.

Plot 'U' 30,755 at £1......

.8545,776 30,755

Two of the lots obtained by filling in Bowrington Canal,

the third being reserved as an

open space

-

50,925 square feet

at 81.50.

76,387

652,918

Balance available..

.897,418.

16.

From the foregoing figures it appears that, even if the scheme should turn out less favourably than anticipat- -ed, the great improvements which have been described can be effected at little or no cost to the Colony whilst there is good reason to believe that a substantial profit would accrue from

their execution.

17.

I am sending a copy of this Despatch to Sir Henry May, and you may desire in order to avoid undue delay to carry on any further negotiations with Sir Robert Jardine or his

representatives