Copy of paragraph No.2 Consulting Engineers

Letter No.72 dated 26th September 1907.

We beg to draw your attention to the following clerical errors which we have come across in the printed copy of the estimate. The total on page 81 of $5,401.00 has been carried to the summary in page 78 as $5,391.00.

The total for VIII.b. $35,980.00.

This will make

In carrying this total to the main summary on page 12 the 5 and 9 have been reversed and it stands $39,560.00.

When the corrections for the above are made the total becomes $8,000,052.63 instead of $8,003,642.63.

On page 87 there appears to be an error in the heading which we think should read as follows:-

Main Head X. Engineering Charges. Sub-Head (a) Engineering (1) Work. Engineering Staff.