# Kowloon Canton Railway. British Section. Estimate.

Main Head Sub. Head Bridges. Winer Bridge No.31. Work One 73 ft. Arch at chain. Item DESCRIPTION quantity Unit Rate AMOUNT 1 Excavation in foundations 10,100 10/ $101.00 2 Timbering and strutting 3 Concrete in foundations 300 30/- $7,300 4 Masonry in superstructure 1,732 3,000 5 Masonry in Arch 1,800 08 $1,440 6 Masonry in coving 140 10/ $8.00 7 Dry stone backing 2,800 Total $8,431.00 Contingencies 10% $843 Grand Total $9,274.10