Main Head.

Sub. Head.

Bridges,

Minor Bridge No.39.

32.

Work

One 5 ft Arch at ch.89*600

Drawing C.R.E. No.269"

AMOUNT.

Quantity. DESCRIPTION. Rate. Unit. Cts. 9,300 Excavation in foundations. 35/- 1,435.00 4,100 Timbering and pumping. 40/- % 2/- 0.ft 1,380.00 3,450 Concrete in foundations. 1,920.00 Masonry in superstructure. 10/- #60 Masonry in Arches. 240.00 130 Masonry in coping. 11 30 8 8 8 8 8 8 8 9 1,130 Dry stone backing. 10 93.00 300 Total 5,379.00 Contingencies 10% 537.93 Grand Total 5,917.23