Jones C.R. E. No. 24.
Kowloon Canton Railway.
BRITISH SECTION.
ESTIMATE.
Main Head.
Bridges.
Sub. Head
Hinor Bridge No.11.
*
Two 3 ft 8in Culverts at ch.27*550 Drawing C.R.E. No.111*
B2.
Work
Quantity DESCRIPTION Rate Unit Amount 9,700 Excavation in foundations, 10/ Cts. 97 Timbering and pumping 7,300 Concrete in foundations, 11,800 Masonry in Superstructure. 38/ 300 Masonry in coping. 880 Dry stone pitching. 2/- 10/ xxx 2,555 4,600 120 Total 7,677 80 Contingencies 10% 767 78 Grand Total 8,445 58