mC.R.E. No. 24.

Kowloon Canton Railway.

BRITISH SECTION ESTIMATE.

Main Head Sub. Head Work Bridgework. Hiner. Bridge No.45. Two 12 ft. span girder bridges landed at Kowloon, at peg 94'700. Quantity DESCRIPTION Unit Rate AMOUNT 7,600 Excavation in foundations. 10/- $76.00 2,980 Punwring and shuttering. 2,580 Concrete in foundations. $1,000.00 $2,580.00 Masonry in superstructure. 35/- 100 Masonry in headstone and coping. 40 $1,023.60 1,180 Dry stone backing. $1,154.00 Two Span girder bridges landed at Kowloon, Transport, erection & painting. $300/- each $600.00 Total $4,297.10 Contingencies 10% $429.71 Grand Total $4,726.81