C.R.E. No. 24.
Kowloon Canton Railway.
BRITISH SECTION
ESTIMATE.
Main Head
Bridgework.
Sub. Head
Major Bridge.
Bridge No.4.
One
Work
Bridge at pag 3*455, over Road.
Quantity. DESCRIPTION. N. Rate. Unit. AMOUNT. 94 -≈ 60' span & 2o x 10a arches. $ Cts. Excavation in foundations. 27,500 Item Pumping and timbering. 300 Concrete in foundations. 2/- 0.ft. 600 00 6,350 Masonry in footings. 10/- oft 6,405 00 19,950 Masonry in superstructure. 135/- 7,980 00 870 Masonry in coping,caps,hadstones etc. 140/- 1,740 00 2,790 Masonry in arches. 2,000 00 5,580 00 40 Dry stone backing. 10/- 40 30 Item Span of Girders 80' 6" landed at Kowloon. Transport, erection & painting. 4,030 Total 32,120 30 Contingincies 10% 3,212 03 Grand Total 35,332 33