C.R.E. No. 24-
Kowloon Canton Railway.
BRITISH SECTION
ESTIMATE.
93
Main Head
Sub. Head
BRIDGES.
MAJOR BRIDGE No.33
Work: Two 40 ft and two 60 ft Girders at ch.74.500 Drawing C.R.E.206B1.
Quantity DESCRIPTION Rate Unit $ Cts. 45,000 Excavation in foundations. Timbering and pumping. 0 650 55,500 Concrete in foundations. Masonry in superstructure 970 Masonry in coping bedstones &c. 80,000 Pitching slopes. 2/- 0.ft 1 2 40 ft Girder landed in Kowloon. #1 2 40 ft Girders erection & painting. 1750/- each 3,500 00 2 60 ft Girders landed in Kowloon. 4000/- each 8,000 00 2 60 ft Girders erection & painting. 600/- each 1,200 00 10/- 35/- 7,227 22 22,200 00 1,940 00 200 Total 51,517 50 Contingencies 10% 5,151 75 Grand Total 56,669 25