Kowloon Canton Railway. BRITISH SECTION ESTIMATE. 87

Main Head Bridges.

Sub. Head Major No.47.

Work One 60' 0,(T) and four 201 0.D. at Chain 108:225.

DESCRIPTION Quantity Unit Rate Cts. AMOUNT Excavation in founds. 61000 10/- 610 00. Timbering and Pumping. 1000 00. 2800 Concrete in founds. 35/ 4480 00. Masonry in Footings. 4850 40/- 1940 00 Superstructure. 21350 40/- 8540 00. Coping and Bedstones. 410 2/- 8.0 00. Dry Stone behind abuts. 700 10/- 7 00 One 60' Span Girder landed in Kowloon. 1 5500/- each 5500 00. Four 201 Span Girders landed in Kowloon. 4 500/- 2000 00. One 60' Span erection and painting. 1 1000/- 1000 00 Four 201 Span erection and painting. 4 100/- 400 00. Total 26297 00. Contingencies 10% 2629. 70 Grand Total 28926 70.