Kowloon Canton Railway.

BRITISH SECTION

ESTIMATE.

Main Head Bridges,

Sub. Head Major No.13.

C.R.E. No. 24.

Work Four 30' Arches Pier Abuts

C.R.E. No.1061.

Quantity DESCRIPTION Rate Unit AMOUNT 180 mt Excavation in founds. 10/- mt $1800.00 Timbering and Pumping. $2500.00 8550 Concrete in founds 35/m $2992.00 2000 Masonry in Footings. 40/- $800.00 20000 Superstructure. 40/- $8080.00 10950 Arches. 2/- a.ft. $21900.00 1100 Coping. $5300.00 Dry Stone Pitching. 2/- 0.ft. $2200.00 10/ 10% $530.00 Total $39502.50 Contingincies 10% $3950.25 Grand Total $43452.75