Forte C.R.E. No. 24.
Kowloon Canton Railway.
BRITISH SECTION
ESTIMATE.
Main Head Bridges.
Sub. Head Major No.8.
Work Tour 20' Archos with Pier Abut at Chain 12:150
DESCRIPTION Quantity Rate Unit AMOUNT C.R.E. No.9531. Cts. Excavation in founds. Timbering and Pumping. 5000 1:6 1:cu 8300 00. Concrete in founds and over Arches. 4550 1.650 7507 50. Masonry in Footings. 19500 35/ 6825 00. Superstructure. 1 £ 10/- for 250 40/- 40/- Arches. 850 2/- 0.ft. 1700 00. Coping. Dry Stone Pitching. 6100 10/- 2/ c.ft. 610 00. Total 29407 50. Contingencies 10% 2940 75. Grand Total $32348 28.